Timeline

Home » Timeline

Cool Timeline

2018
March 16

Commercial Start

16th March, 2018
March 8

Reliability Tests Completed

8th March, 2018
March 1

Reliability Tests Started

1st March, 2018
February 22

First WTG Commissioned

22nd February, 2018
February 1

Energization

1st February, 2018
2017
December 6

WTG Installed

6th December, 2017
November 15

Building Structure Completed

15th November, 2017
August 10

WTG Installation Started

10th August, 2017
May 10

First WTG Foundation

10th May, 2017
May 4

1st Anchor Cage Installed

4th May, 2017