Timeline
Home »
PROJECT MILESTONES ACHIEVEMENT AT A GLANCE…..
2018
Commercial Start
16th March, 2018
Reliability Tests Completed
8th March, 2018
Reliability Tests Started
1st March, 2018
First WTG Commissioned
22nd February, 2018
Energization
1st February, 2018
2017
WTG Installed
6th December, 2017
Building Structure Completed
15th November, 2017
WTG Installation Started
10th August, 2017
First WTG Foundation
10th May, 2017
1st Anchor Cage Installed
4th May, 2017
Civil Works Started
4th February, 2017
WTG Contract Execution Start
6th January, 2017
2016
Project Start Date
19th December 2016